KC-X Tanker RFP Out In February
Filed under: Boeing, Congress, EADS, KC-X, KC-X Tanker News, Northrop Grumman Corp.
At a recent press availability the U.S. Air Force Chief of Staff, General Schwartz, said that he expects the final RFP for the KC-X contest to be released next month. He also stated that it will be little changed from the draft RFP. Both Northrop (NOC) and Boeing (BA) have been submitting questions and comments on the draft RFP and some of these will be addressed in the final one. The RFP will be released a few weeks after the 2011 Defense Budget goes to Congress which is planned for 2 February.
Schwarz did say that the final RFP may have changes based on recent comments by Northrop and its partner EADS (EADS:P) that they might not participate as they felt the RFP favored Boeing too much. Both groups had also commented on the use of a fixed price development contract and how it transferred too much risk to the contractor from the Government.
Framework Seems To Have Been Reached To Allow A400M Resolution
Filed under: Business Line, Companies, Countries, EADS, Events, France, Germany, Military Aviation, Restructuring, Services, development program, logistics
Late last week it was announced that EADS and the customers for the A400M transport seemed to have reached a framework to allow talks to proceed that may resolve the funding issues with the program. Due to about two years of development and integration problems the aircraft only achieved first flight in December, 2009 and now will not deliver the first aircraft until 2012. These have caused EADS and its subsidiary Airbus to spend billions beyond the money planned.
The company is trying to work a deal where the customers pay a large portion of the overruns as the initial contract was a Fixed Price one that did not provide enough funding to cover the delays. EADS has spent over five billion Euros of its own money on the program and is hoping that either through price increases or direct investment the seven major European buyers will cover these costs. Recently EADS had threatened to just go ahead and end work on the program and eat the losses rather then continuing it and losing more money.
After a recent meeting it became clear that most of the countries involved are willing to work out some financial deal with EADS and that company will agree to continue talking. There will be a meeting in early February to begin these discussions. The compromise being discussed would see increased production prices and lower quantities for a few years with EADS absorbing some of the cost overruns internally. Then there would have to be a decision point in the future whether to complete the program’s planned total quantity. One of the two FMS customers, South Africa, already canceled their order due to the price increases proposed by EADS.
The A400M is the premier military aerospace program in Europe and it suffered from the optimistic plan to use a fixed price development contract. Not completing it would be seen as a blow to EADS and European defense integration. At the same time all of the customers are facing financial pressure due to the global downturn and increased social spending. At the same time building only a few of the aircraft solves nobody’s problems.
A400M first flight video from signatoryvideos. http://www.youtube.com/watch?v=oX-kIUYRyDk
FCS Cancellation Fallout
Filed under: Boeing, Business Line, Companies, Congress, Events, Federal Budget Process, IT, Restructuring, SAIC, Services, U.S. Army, development program, logistics, production program
The cancellation of the current Future Combat Systems (FCS) development contract was one of the cornerstones of the Obama Administrations 2010 defense budget. The program of new vehicles, unmanned aerial and ground systems, and the data links connecting them was estimated at over $160 billion. The Army still has a requirement for a upgrade to their combat brigades currently using the Eighties produced M1/M2 vehicles and the Styker Interim system. As such a new program was set up to replace FCS almost immediately after the contract with Boeing and SAIC was canceled.
Now the Army is concerned that the money planned for in the budget may not be available for this new program. At a minimum some of it will be needed to pay the termination fees related to the various contracts ended prematurely. They were ended at the convenience of the government so the contractors are entitled to payment for whatever work they had done and what it takes to close out the contracts. If the money doesn’t remain in the FCS line then the Army will be forced to fund it from other programs.
Congress in their mark up of the 2010 budget cut most of the money budgeted for this as they felt there were sufficient current funds to cover this. This may be a little too much penny save pound foolish. The Army knows fairly well what is needed and probably budgeted appropriately. The cost to other parts of the Army including the new modernization program may be quite high.
Fixed Price for DDG-1000
Filed under: Business Line, Companies, Congress, Contract Awards, Department of Defense, Events, General Dynamics, Maine, Northrop Grumman Corp., Restructuring, Services, States, U.S. Navy, production program
As part of the reforms announced by Secretary Gates’ a few weeks ago one was to end the DDG-1000 program at three ships and restart the DDG-51 production line. General Dynamics will build the last two as the first is under construction by Northrop Grumman. Northrop will get the DDG-51 work to make up for the cancellation. The New York Times is reporting that GD agreed to a fixed price contract for hulls numbers two and three.
Normally fixed price contracts are used for when full rate production gets underway. The first few batches of a product are made as part of the cost plus development contract. This spreads the risk to the Government. Obama has said he wants more fixed price contracts to save money on defense programs that tend to go over schedule and cost. Of course a lot of that is due to issues with requirements or testing or just making the thing that add time and money.
DoD uses two ways to look at unit cost when it comes to managing a program. One is the total of all procurement and R&D funding spread over the quantity of the items being bought. Another just takes the total procurement cost and divides that by the quantity. As you build more of an item the R&D is spread over more units slowly lowering that cost. If things begin to require more procurement then that cost goes up. Slowing down a program and buying the same quantity over a longer time effectively increases total program costs greatly. There is always some fixed cost applied each year if you build one, ten or a hundred of an item. The more years it takes the more those fixed costs add up.
With this program it may be OK to use a FFP contract as the costs are more known and fixed. If there are issues GD will be taking a risk as they might not get back all the money it takes them to build the ships. This is why Cost Plus contracts are used for development and ironing out production. In this case it will be an interesting experiment to see if it works out for the Government and the contractor.
Europeon nations developing common UAV
Filed under: EADS, France, Military Aviation, S, development program
This article describes how EADS is moving forward on a development contract for UAV for Germany, Spain, and France. They have finished the study phase and are now working on risk reduction. Ultimately, if all things go well they will move into production of a UAV for all three nations. There is no discussion as to how they will integrate the requirements of the different countries, or perhaps they will all accept the same solution. As in most programs EADS will have to produce a certain number of aircraft to make back some of the money sunk into the development.
Boeing expands JLTV team
Boeing added SAIC and Ford to the team they have established to bid on the development contract for the JLTV. See an article here. The JLTV will replace the HUMVEE and other light tactical vehicles. Read more
Alion Awarded $7M Contract to Support Navy’s Improved Live Virtual Constructive Integration Research Program
Filed under: Syndicated Industry News
L-3 Awarded Army Technology Contract for Bradley Fighting Vehicles
Filed under: Syndicated Industry News
U.S. Army Natick Soldier Systems Center Extends Body Armor Development Contract with Nanocomp Technologies
Filed under: Syndicated Industry News



